Construction activity on the Ring Road 2.5 section passing through Cau Giay ward is very bustling. (Photo: thanhuyhanoi.vn)
Contractors are concentrating manpower and machinery to complete the roadbed, surface, median strips, and technical infrastructure, aiming for the technical opening of the Ring Road 2.5 section through Cau Giay ( Hanoi ) on October 10th.

Currently, the contractor has completed over 80% of the work. The construction unit is striving to essentially complete the entire route before October 10th. (Photo: thanhuyhanoi.vn)
Once the route is operational, the transportation infrastructure in western Hanoi will have another important link, contributing to the distribution of traffic flow and improving the urban landscape.
According to the design, the road has a cross-section width of 50m, of which the vehicle lane is 31m wide, the central median is 3m wide, and the sidewalks on both sides have a total width of 16m.

Upon completion, the project will contribute to reducing traffic congestion during peak hours, improving urban connectivity, and promoting socio -economic development. (Photo: thanhuyhanoi.vn)
When completed, this will be a crucial segment in the gradual completion of the Belt and Road Initiative 2.5.