The inspection team was led by Mr. Ha Thai Tho, Deputy Head of the Legal Affairs Committee of the Provincial People's Council. Representing Gia Phu commune were the commune leaders, representatives from specialized departments, and the Party branch secretary and village head of the area where the project was being surveyed.

baolaocai-br_dsc07131-9017.jpg
baolaocai-br_khaosat-8262.jpg
The working group surveyed two rural road construction projects in Gia Phu commune.

The survey team examined the Giao Tien rural road (now part of Tien Cuong village) and the Mo village rural road (now part of Cu Ha village). On-site, the team inspected the condition of the road surface, construction quality, progress, and auxiliary items of each project.

The Giao Tien route is 801 meters long, with approximately 150 meters remaining unfinished. The Mo village road is 480 meters long and is currently under construction.

Through the inspection, the delegation noted and highly appreciated the quality of construction on the inspected roads. The delegation requested the People's Committee of the commune to coordinate with relevant units to urge the contractor to allocate manpower and equipment, accelerate progress, and complete the items according to the design, especially the road shoulders and drainage system. Construction must ensure technical requirements, quality, and safety to quickly put the roads into use, meeting the needs of people for travel, trade, and goods transportation.