The delegation from the Lao Cai Provincial Joint Task Force (Vietnam) was led by Mr. Ho Cao Khai, Deputy Director of the Department of Construction; the Chinese delegation was led by Mr. Yang Zelong, Deputy Director of the Department of Transportation of Yunnan Province.

baolaocai-br_1795487941605-1218288131405634485-1218288131405634485-0e31ab3ef9d3880ffa1036f1cf1d6d24.jpg
The scene at the meeting. Photo: Contributor

Construction of the road bridge across the Red River between Bat Xat (Vietnam) and Ba Sai (China) commenced on March 31, 2025. To date, both sides have completed the entire substructure. The Vietnamese side has completed abutment M2 and piers T9 and T8; the Chinese side has completed abutment M0 and piers T6 and T7.

Regarding the superstructure, both sides have completed the 40-meter cast-in-place girder section on scaffolding, block K0, and girder segments K1-K13; segment K14 is currently under construction. The Vietnamese side expects to complete the concrete pouring for segment K14 between November 30th and December 5th, 2026, after which they will hand over the site to the Chinese side to prepare for the construction of the connecting segment of the middle span of the main bridge. The Chinese side also expects to complete segment K14 within a similar timeframe.

baolaocai-br_1795488348253-1218288131405634485-1218288131405634485-d021cadd70d20c59b939c4e2ffbf783e.jpg
Representatives from the Lao Cai Provincial Joint Task Force participate in the talks. Photo: CTV

During the talks, both sides agreed to urge contractors to ensure progress and complete the construction of the bridge's end span before December 20, 2026; the Chinese side will pour concrete for the main span's end span before December 31, 2026. The specific dates will be announced by the Chinese side to the Vietnamese side five days in advance.

baolaocai-br_1795488446031-1218288131405634485-1218288131405634485-f9fe541a1ec3b71e162603c60c1225b9.jpg
Delegates from the Yunnan Provincial Joint Task Force participate in the talks. Photo: CTV

According to the agreement, the Chinese side will undertake the construction of the main bridge's middle span, including the synchronous tensioning and grouting of 50 bundles of prestressed cables in the bottom slab and 8 bundles of prestressed cables in the surface slab. Both sides will share 50% of the cost of these items. The Vietnamese side is expected to pay 232,053 RMB, scheduled before March 31, 2027.

After the project is completed, both sides will establish a joint quality inspection team to conduct inspections and assess the quality of the bridge. The inspection costs will be split 50% each; the Vietnamese side is expected to pay 152,471 RMB.

baolaocai-br_1795488518151-1218288131405634485-1218288131405634485-e6eaecb966e9f9a7685cd99dcda47af0.jpg
The two sides exchanged a memorandum of understanding agreeing on the plan for joining the two sections of the road bridge across the Red River at the Bat Xat - Ba Sai border. Photo: CTV.

During the talks, both sides also agreed on matters related to warranty responsibilities, supervision of the construction of the bridge's final section, handling of technical issues, construction of railings, lighting systems, and sidewalk paving stones to ensure the project's uniformity and aesthetic appeal.