Key projects accelerate progress.
The construction package for the Tan Vu - Hung Dao - Bui Vien section of the Ring Road 2 project spans over 11 km and has a total investment of over 8,593 billion VND. In the final days of the year, contractors on the construction site are accelerating progress, taking advantage of every hour and day to complete the items according to plan. During implementation, the project has encountered many difficulties due to land clearance issues, material shortages, contractor capacity, and weather conditions.
However, thanks to the decisive involvement of the investor and local authorities, major difficulties and obstacles have been gradually resolved, creating favorable conditions for contractors to focus on construction. It is expected that on November 26th, the Hai Thanh Bridge, currently the widest bridge in Hai Phong , will be officially completed. The remaining construction packages have all reached over 80% completion. Contractors are focusing on completing the final items, striving to ensure quality and put the project into operation by January 31st, 2027. The accelerated construction progress has also contributed to boosting capital disbursement, with the current disbursement rate reaching 95% of the total allocated capital for the project.

In response to the city's requirement to complete the road connecting Dinh Vu Industrial Park with Nam Dinh Vu Industrial Park (Phase II) before the 2027 New Year, since mid-November, the construction contractor, Bach Dang Construction Corporation - JSC, has mobilized maximum manpower, materials, and equipment, while also developing a suitable construction plan to ensure the project's progress.
According to the contractor's representative, the project is being implemented under conditions of simultaneous construction and operation, while the volume of vehicles entering and exiting the port is high. This poses significant pressure on the schedule, requiring relevant units to focus intensely and organize construction flexibly and efficiently. By mid-November 2026, only 21.7% of the planned funds had been disbursed. However, with accelerated construction on the site, the contractor commits to disbursing 100% of the allocated capital by December 31st.
In 2026, Hai Phong identified the disbursement of public investment capital as one of the key drivers to boost economic growth, improve infrastructure, and create room for the city's development. As of November 20th, the total public investment capital disbursed in the city reached 101% of the plan assigned by the Prime Minister (after excluding the 5% savings). With this result, Hai Phong ranked 3rd nationwide in terms of disbursed capital volume and was rated "Very Good" by the Ministry of Finance .
Notably, many investors and localities achieved high disbursement rates. Out of a total of 125 investors and localities, 78 units achieved disbursement rates of 86% or higher, with many exceeding 95%. Several wards and communes had disbursement rates above 95%, including An Phong, Chi Minh, Hong Chau, Kien Hung, Quyet Thang, Hung Dao, Do Son, Hai Duong, Phu Lien, and Duong Kinh…
Prioritize key projects and inter-regional connectivity.

To date, Hai Phong has disbursed 101% of the public investment capital plan for 2026 assigned by the Prime Minister . To strive to exceed the plan by 20%, project owners have just over a month to accelerate disbursement. Through inspections of project progress, city leaders have consistently emphasized that accelerating disbursement must be linked to responsible implementation, compliance with regulations, ensuring project quality, and investment efficiency.
Following adjustments, the total public investment capital allocated to the Hai Phong Transport Construction Project Management Board for 2026 reached over 14,000 billion VND. As of November 20th, the unit had disbursed 81% of the planned amount. To achieve the set goals, the board's leaders regularly monitor construction sites, inspect and expedite progress, and promptly resolve difficulties and obstacles related to land acquisition, material sources, and technical infrastructure.
In addition, the Steering Committee directed contractors to supplement manpower and machinery, organize multiple construction teams, increase shifts and overtime; proactively adjust construction plans, and make the most of favorable weather conditions to accelerate progress. Guidance and management were maintained regularly and continuously, linking progress to the specific responsibilities of each department and officer in accordance with the "6 clear principles".

According to a resolution of the City People's Council, the total public investment capital managed by the city in 2027 is VND 38,760 billion (excluding supplementary capital). In the context of expanding urban space and increasing connectivity needs, Hai Phong has identified key areas for investment in strategic infrastructure projects, in line with the policies of the Politburo , the Government, and the City Party Committee. These projects play a crucial role in reorganizing the socio-economic space and contributing to the city's goal of achieving a 13% GRDP growth rate during the 2026-2030 period.
The city prioritizes resources for many key transportation projects such as: the East-West connecting route; the Hanoi -Quang Ninh high-speed railway; the Lao Cai-Hanoi-Hai Phong railway; Ring Road 3; the connecting route from Rao 3 Bridge to the coastal road section from Bui Vien Street to Provincial Road 363; the coastal road through Hai Phong from Provincial Road 353 to Thai Binh Bridge (Km0 - Km19+645)... These are all important projects in completing the transportation system, strengthening regional connectivity and improving the quality of life for the people.
With the spirit of "only discussing action, not retreating," and "not putting off today's work until tomorrow, resolving issues as they arise," Hai Phong is focusing all resources and is determined to exceed the 20% public investment plan assigned by the Prime Minister. This result will create further momentum for the city to enter 2027 with the determination to achieve higher development goals.
In the final stretch, projects, from key infrastructure projects to grassroots projects, must not only accelerate progress but also ensure quality, safety, and investment efficiency. Upon completion, these projects will contribute to improving the transportation network, strengthening connectivity between economic regions, expanding development space, attracting investment, and promoting socio-economic growth in Hai Phong.