The Thang Long Project Management Board (Ministry of Construction) has just approved the results of the contractor selection for the feasibility study report of the North-South high-speed railway project. A consortium of Vietnamese, French, and Korean contractors won the bid with a price of over 10,200 billion VND, and the contract implementation period is 30 months.

According to Mr. Nguyen Trung Son, Deputy Director of the Thang Long Project Management Board, after selecting the consulting unit, specific timelines have been determined. Accordingly, within the 30 months of the contract, the consulting consortium must complete four main milestones.

Four key milestones for the North-South high-speed railway project to commence construction by the end of 2028 - Image 1.

A high-speed railway line in China.

PHOTO: MAI HA

Specifically, by the third month, the consultant must propose applicable standards and design requirements. This is the first step in determining the technical standards system, which will serve as the basis for carrying out subsequent survey, calculation, and design work.

In the 13th month, the consultant will submit a mid-term report, which proposes route selection, locations of control points, and technological options. This is crucial, shaping the main technical solutions of the project before finalizing the feasibility study report.


By the 27th month, the feasibility study report will be submitted to the Appraisal Council and the Ministry of Construction for review. By the 30th month, the report will be approved by the competent authority.

From Q1 to Q3 2027, the investor will direct consultants and relevant parties to focus on surveying the topography and geology along the route. Simultaneously, the land acquisition boundary documents will be prioritized for early handover so that localities have a basis to implement compensation, support, and resettlement in 2027.

If the above schedule is followed, the North-South high-speed railway project is expected to begin construction by the end of 2028.

Previously, the Thang Long Project Management Board issued a decision approving the results of the contractor selection for package TV-02, which includes consulting services for surveying and preparing a feasibility study report (including FEED design and preparation of tender documents).

The consortium consists of four foreign contractors, led by SYSTRA (France), along with Sambo Engineering Co., Ltd (SAMBO), Yooshin Engineering Corporation (Yooshin), and Korea National Railway (KNR) of South Korea.

On the Vietnamese side, the participating companies include the Transport Engineering Design Consulting Corporation (TEDI), the Southern Transport Engineering Design Consulting Joint Stock Company (TEDI SOUTH), the Transport Investment and Construction Consulting Joint Stock Company (TRICC), and Hoang Long Construction Consulting Joint Stock Company (HOANG LONG).

The North-South high-speed railway project is 1,541 km long, connecting Ngoc Hoi station (Hanoi) with Thu Thiem station (Ho Chi Minh City), passing through 15 provinces and cities. The line will be a double-track line with a 1,435 mm gauge, a design speed of 350 km/h, a load capacity of 22.5 tons per axle, and will include 23 passenger stations and 5 freight stations.

The preliminary total investment for the project is $67.34 billion. According to the plan, the feasibility study report will be prepared and approved between 2026 and 2028, with the project essentially completed in 2035. Previously, the government aimed to start construction by the end of 2026; however, the selection of a consulting contractor has been delayed due to several obstacles.