Sequence, procedures, and authority for appraisal and investment decision-making for component projects.

The Minister of Construction and the Chairpersons of the People's Committees of the provinces and cities of Hanoi, Hai Phong, Bac Ninh, Ninh Binh, Hung Yen, Thai Nguyen, and Phu Tho shall exercise their authority as investment decision-makers, organize the preparation, appraisal, and approval of feasibility study reports for the component projects (listed in Appendices 1 and 2 attached to this Resolution).

During implementation, the managing agencies are required to continue researching and evaluating the investment methods for the component projects under the public-private partnership model to select the appropriate investment form and strengthen the mobilization of capital sources outside the state budget.

Central government budget funds allocated for the period 2026-2030 shall not exceed VND 61,394 billion for investment in the main expressway section (approximately 116 km within the territory of 4 provinces and cities: Hai Phong, Bac Ninh , Ninh Binh, and Hung Yen), and shall not be used for compensation, support, resettlement, or investment in the construction of parallel roads.

The proposed investment for the Hanoi Capital Region's Ring Road 5 project includes a 6-lane road with parallel lanes on both sides - Illustration image.

Specific tasks of ministries, departments, and localities

The Ministry of Construction is the lead agency responsible for organizing and implementing the Project, ensuring its consistency and overall coherence; providing technical support, coordinating the resolution of difficulties and obstacles related to specialized technical issues (regulations, standards, technical solutions, etc.), and urging the localities assigned as managing agencies to ensure quality and progress as required during implementation.

At the same time, the Ministry of Construction will take the lead in developing and issuing regulations on coordination between the Ministry of Construction and the managing agencies; and will direct and coordinate with the managing agencies in developing and issuing plans for the implementation of the component projects.

Fulfill the responsibilities of state management in construction and the responsibilities of the Ministry managing specialized construction projects as stipulated by construction law .

The presiding authority, in coordination with local authorities, shall propose funding sources and allocation schedules for the main expressway component projects, meeting the required progress for the component projects in the 2026-2030 investment period, and submit them to the Ministry of Finance for compilation and reporting to the Government. The Prime Minister shall assign the medium-term public investment plan using central government budget funds for the 2026-2030 period, prioritizing the allocation of state budget funds for the 2031-2035 period to continue investing in the Project.

In addition, the Ministry of Construction, in coordination with the Ministry of Finance and relevant localities, will study options for converting the investment form and report to the Government for consideration and decision in accordance with the authority granted by the National Assembly in Clause 9, Article 3 of Resolution No. 38/2026/QH16.

Based on reports from the managing agencies, if adjustments to the central government budget allocation among component projects are necessary, the Ministry of Construction will take the lead in compiling and proposing adjustments to the allocation of funds between component projects using central government budget funds, ensuring the project's progress, while not exceeding the preliminary total investment approved in Resolution No. 38/2026/QH16. This proposal will be submitted to the Ministry of Finance for compilation and reporting to the Government.

The Ministry of Planning and Investment is responsible for compiling data and reports from localities on the methods of revenue collection from the development of industrial parks, urban areas, functional zones, and urban development zones in the vicinity of Ring Road 5. This data will be submitted to the Ministry of Finance for consolidation and presentation to the Government for the issuance of regulations and specific guidelines on the revenue sharing ratio and implementation methods for the aforementioned projects.

Based on proposals from the Ministry of Construction and local authorities, the Ministry of Finance will compile a report for the Government to allocate the medium-term public investment plan for the 2026-2030 period to the component projects of the expressway; and compile a report for competent authorities to prioritize the allocation of state budget funds to continue investing in the Project. During implementation, the Ministry will advise the Government on the use of legal funding sources within its authority to ensure sufficient capital is allocated in accordance with the implementation schedule, preventing the Project from being halted or suspended due to insufficient funding; and ensuring consistency with the state budget balance for each period and the national public debt borrowing and repayment plan.

Based on proposals from the Ministry of Construction and localities, the Ministry of Finance will compile and report to the Government on the allocation of capital among component projects using central government budget funds to ensure the progress of the Project, on the principle of not exceeding the preliminary total investment of the Project approved by the National Assembly in Resolution No. 38/2026/QH16.

The Ministry of Finance is responsible for guiding and resolving issues within its authority, or advising competent authorities on resolving difficulties and obstacles related to its specialized field of responsibility.

Based on proposals from localities, the Ministry of Construction will compile and submit them to the Ministry of Finance for presentation to the Government to issue regulations and specific guidelines on the allocation ratio and implementation method for revenue from the development of urban areas and functional zones surrounding the road as stipulated in Clause 8, Article 3 of Resolution No. 38/2026/QH16 in 2027.

Guidelines for the provision of advances from local budget funds for central government budget expenditures in situations where central government budget funds have been allocated but not yet disbursed; the central government will reimburse the funds once they are allocated.

In the Resolution, the Government also assigned tasks to the Ministry of Agriculture and Environment, the Ministry of National Defence, the Ministry of Public Security, Vietnam Electricity Corporation, and the People's Committees of the provinces and cities of Hanoi, Hai Phong, Bac Ninh, Ninh Binh, Hung Yen, Thai Nguyen, and Phu Tho.

According to Resolution No. 38/2026/QH16, the project has a length of approximately 349 km, passing through the territories of 7 provinces and cities including: Hanoi, Ninh Binh, Hung Yen, Hai Phong, Bac Ninh, Thai Nguyen and Phu Tho. The project is implemented in the form of public investment with a total investment of approximately 288,268 billion VND.

The objective is to establish a highway connecting Hanoi with localities in the region to meet sustainable transportation needs, create a driving force for economic development, open up new opportunities for economic growth; create a foundation for socio-economic development, ensure national defense and security; divert traffic from afar, contributing to reducing traffic congestion and environmental pollution; complete the Hanoi ring road system and successfully achieve the goals and tasks set forth in the Resolution of the 14th National Congress of the Communist Party of Vietnam and other Party resolutions.