In Lanh village, Sop Cop commune, the renovation and repair of the village's cultural center is being urgently implemented by the construction unit. After the merger of Cang, Lanh, and Phong villages into Lanh village, the population has increased, and the need for community meetings and activities is growing, while the old cultural center no longer meets the actual requirements. Given this situation, at the end of October 2026, the project to renovate and repair the Lanh village cultural center was launched, with a total investment of 2 billion VND, constructed by Ha Soi Co., Ltd.
Mr. Vi Van Thuong from Lanh village shared: "Previously, the community center was not large enough to accommodate large gatherings. Now, with the government's investment, the people are very excited and hope the project will be completed soon to serve the propaganda activities, cultural and artistic events, and meetings of the people."

Immediately after taking over the site, Ha Soi Co., Ltd. mobilized manpower, machinery, and equipment to organize construction. Mr. Doan Dang Quyen, a technical officer of the company, said: "The unit is focusing its manpower and accelerating the progress of the items, striving to complete the project ahead of the contract deadline, expected to be handed over on December 31, 2026, while ensuring quality and technical requirements."
Along with the construction of the cultural center, Sop Cop commune has focused on implementing many projects related to transportation, irrigation, and clean water, contributing to solving the essential needs of the people. A prime example is the 370-meter-long embankment project to prevent landslides in the commune center, connecting the Hua Muong village spillway bridge to the Sop Cop concrete bridge. With a total investment of over 14 billion VND, the project has been completed and put into use. This project helps protect residential and agricultural land and essential infrastructure, ensuring safety for more than 500 households in the area.

Mr. Lo Trung Thanh, from Hua Muong village, Sop Cop commune, said: "Previously, whenever there was heavy rain and floodwaters rose, the residential area frequently faced the risk of landslides, affecting houses and crops. Now that the embankment project has been completed and put into use, people feel more secure when the rainy season and floods come."
In 2026, Sop Cop commune was allocated a total public investment capital plan of over 21.95 billion VND, focusing on projects in the fields of transportation, irrigation, water supply, culture, and essential infrastructure. As of November 11th, the total disbursed capital reached over 8.46 billion VND, equivalent to 41.29% of the allocated capital plan. Of this, the provincial budget disbursed over 3.38 billion VND, reaching 43.5%; the commune budget disbursed over 4.86 billion VND, reaching 38.17%. For the National Target Program on New Rural Development, Sustainable Poverty Reduction, and Socio-Economic Development, the disbursement rate reached 59.47%, equivalent to over 2.75 billion VND. The National Target Program on Cultural Development disbursed over 1.21 billion VND, reaching 32.47%. Some projects achieved positive disbursement results, such as: the road to Hua Lanh village and the irrigation canal project in Na Nghe village have completed 100% of the planned capital disbursement; the irrigation project at Som Poi dam in Poi Lanh village reached 80.69%; and the water supply project in Na Mon village reached 80.54%.

Besides the achievements, the disbursement progress of some projects is still slow, mainly due to some funds being allocated in the third quarter of 2026, leaving a short remaining implementation time. The stages of investment preparation, document completion, construction, acceptance, and payment need to be carried out in full accordance with regulations. Furthermore, the handover of land for some irrigation projects depends on the rice harvesting schedule of the people, affecting the construction process. To overcome these difficulties, the People's Committee of the commune has assigned the Economic Department to coordinate with project management units, supervisory consultants, and contractors to regularly review the progress of each project, update construction volume, acceptance, and payment weekly; and promptly advise on resolving obstacles, especially for projects at risk of delays. At the same time, strengthen on-site inspections, coordinate with people to agree on the land handover time, creating conditions to accelerate construction progress and disburse public investment funds. Expeditiously complete the acceptance and payment documents when all conditions are met.
Mr. Duong Dinh Nghi, Vice Chairman of the People's Committee of Sop Cop commune, informed: The commune has directed specialized agencies to focus on preparing investment conditions, regularly inspect and monitor the progress of each project; requiring construction units to mobilize manpower and machinery, accelerate progress, and ensure the quality of the works. The commune strives to disburse a cumulative amount of over 15.5 billion VND by November 30th, reaching approximately 75.6% of the allocated capital plan; and to complete the disbursement of 100% of the 2026 public investment capital plan by December 31st as committed to the Provincial People's Committee.
Under the guidance of the Party Committee and the government, with the coordination of relevant units and the consensus of the people, Sop Cop commune is focusing on overcoming difficulties, accelerating the construction progress and disbursement of funds for projects. This will maximize the effectiveness of public investment capital, promote socio-economic development, and improve the lives of people in the border region.