In mid-November, at Long Thanh International Airport, numerous preparatory activities for operation and accelerated construction were being carried out simultaneously.

Long Thanh Airport activates trial runs of various operational scenarios, awaiting its

Relevant units are implementing scenarios for passenger service at Long Thanh Airport.

As part of the ORAT pilot program, Long Thanh International Airport has implemented the 1TO-11 scenario for passenger service in phase 1, including both domestic and international operations.

The program was designed with three simulated flight scenarios: domestic departures, international departures, and international arrivals. With the participation of 50 simulated passengers and relevant personnel, the entire service process was examined, from airline check-in and boarding pass verification to security screening, immigration, health quarantine, and customs procedures.

In addition, the units also checked the ability to coordinate and exchange passenger and baggage data through each stage such as check-in, security checks, and boarding. The operation of the control system at the gates and passenger announcements was also reviewed to ensure that all operational processes were synchronized.

Previously, the airport, in coordination with the consulting firm IAC and relevant units, conducted a trial run of the 1TO-30 scenario, testing the aviation beacon system (AGL). Working groups coordinated to inspect the runway lighting system and rapid exit taxiways, while also practicing communication and reporting procedures between locations.

Long Thanh Airport activates trial runs of various operational scenarios, awaiting its
Long Thanh Airport activates trial runs of various operational scenarios, awaiting its
Long Thanh Airport activates trial runs of various operational scenarios, awaiting its
Long Thanh Airport activates trial runs of various operational scenarios, awaiting its

Simulated scenario and inspection/handling procedures at Long Thanh Airport runway.

A simulated scenario involving a malfunctioning runway center light was also included in the drill. Maintenance teams practiced approaching the repair area, checking for foreign objects on the runway, and reporting after leaving the area.

In addition, ACV, relevant units, and Dong Nai province are also actively implementing coordination in port operations, synchronizing transportation connections, ensuring aviation security, maintaining public order, fire prevention and control, controlling UAVs, and arranging accommodation for aviation personnel.

Alongside the trial runs, activities connecting with airlines and the international business community have also been strengthened. Long Thanh International Airport welcomed delegations from Qatar Airways and Turkish Airlines to visit and learn about the functional areas at the passenger terminal.

In addition, the Port also welcomed representatives from the American Chamber of Commerce in Vietnam (AmCham Vietnam), the U.S. Consulate General in Ho Chi Minh City, and U.S. businesses operating in the aviation, logistics, infrastructure, and transportation sectors. During the meeting, the delegation learned about the project's progress, operational direction, and preparations for operation, while also touring the construction site and discussing opportunities for cooperation.

Long Thanh Airport activates trial runs of various operational scenarios, awaiting its
Long Thanh Airport activates trial runs of various operational scenarios, awaiting its
Long Thanh Airport activates trial runs of various operational scenarios, awaiting its

Many activities are being implemented simultaneously at Long Thanh International Airport.

To prepare the workforce for operation and exploitation, Long Thanh International Airport continues to recruit employees in 2026 for the following positions: maintenance and repair staff for technical equipment; maintenance and repair staff for infrastructure; and operation staff for technical equipment.

Many items are accelerating towards the finish line.

During this period, contractors are focusing on the construction and equipment installation at the Long Thanh airport passenger terminal, aiming to bring the airport into commercial operation from 0:00 on December 24th.

Currently, the passenger terminal construction project is approximately 90% complete. Items being expedited include plastering, waterproofing, painting, tiling, ceiling and partition construction, interior design, and landscaping.

Long Thanh Airport activates trial runs of various operational scenarios, awaiting its

A modern screening system has been installed.

For the electromechanical system, the construction and installation volume has reached over 96%. Meanwhile, the installation of passenger terminal equipment systems has reached over 80%, with many important systems being completed and put into trial operation.

For the baggage screening system (HBS), the contractor has brought in various equipment to the construction site, such as X-ray machines and explosive detection devices (ETDs). Many of these devices have already been installed.

The systems supporting aircraft operations are also being finalized. The Aircraft Parking Assist System (ASE) has been connected and is undergoing testing.

130 aircraft docking guidance systems (VDGS) have been delivered to the construction site, with approximately two-thirds already installed. All 108 escalators and stairwells have been installed. For the elevator system, the contractor has essentially completed the mechanical installation.

According to ACV, Long Thanh Airport is being developed according to the "Smart-Green Airport" model, aiming for international 5-star standards, with the application of many technologies in passenger services and operational management.

Long Thanh Airport activates trial runs of various operational scenarios, awaiting its
Long Thanh Airport activates trial runs of various operational scenarios, awaiting its

Construction, installation, and equipment testing activities are also being accelerated at Long Thanh Airport.

The highlight is the seamless digital travel model, applying biometric technology from check-in and self-baggage drop-off to departure. The systems are designed to connect with VNeID and the national population database, gradually implementing a "paperless travel" model.

In terms of operations, the airport is equipped with an automated baggage handling system (BHS) with a total conveyor belt length of approximately 24km, directly connected to the terminal infrastructure. The Smart Airport Operations Center (Smart APOC) plays a key role in coordinating operational activities. Meanwhile, automation systems in the security check, immigration, and boarding areas contribute to shortening processing times and ensuring safety.

Vehicle management technologies are also integrated, including a cashless toll collection system, smart parking lots utilizing AI cameras, and a real-time traffic control system.

Long Thanh Airport is being built in Long Thanh Ward, Dong Nai City, on an area of ​​approximately 5,000 hectares. Upon completion of all phases, the airport is expected to have a capacity of 100 million passengers and 5 million tons of cargo per year, aiming to become a major air transit hub in Southeast Asia.

According to the plan, Long Thanh Airport is expected to begin partial operation from 0:00 on December 24, 2026. In the initial phase of operation, the western wing and the central passenger terminal area will be prioritized for completion.

Here, four check-in islands are designated to serve both domestic and international flights. From December 2026 to March 2027, Long Thanh Airport is expected to serve both domestic and international flights, with a scale of approximately 20-30 flights per day.