Thanks to public investment funds, many roads and public works in Uong Bi ward have been upgraded and renovated, meeting the transportation and living needs of the people. A prime example is the Ly Thuong Kiet street renovation project, which commenced at the end of May 2026, with a total length of nearly 450 meters. The project included comprehensive investment in various components such as asphalt paving, drainage system completion, underground electrical system installation, and sidewalk renovation. After more than 3 months of construction, the Ly Thuong Kiet street renovation project was completed and put into use on schedule. The project not only contributes to ensuring traffic safety but also improves the landscape, creating a more attractive appearance for the area and gradually enhancing the quality of urban infrastructure in the ward.
Along with Ly Thuong Kiet street, Uong Bi ward has focused on implementing many other traffic, urban beautification, and public infrastructure projects. Some projects have been completed, such as upgrading and repairing the drainage ditch from behind Quang Trung Primary School to the intersection of Quang Trung 5A neighborhood; upgrading and expanding the concrete road and drainage ditch in alley 118B, Bai Dai street; repairing and renovating the road in alley 180, Thanh Son street, Thanh Son 4 neighborhood... These projects contribute to improving traffic conditions, drainage, enhancing the quality of community living spaces, and meeting the practical needs of the people.
According to the report from the Uong Bi Ward Service Supply Center, the total capital investment plan for basic construction in 2026, after adjustments and additions, is 366.11 billion VND. The capital is allocated to ongoing projects, newly started projects, additional projects during the year, and planning and investment preparation tasks. In addition, the locality has also taken over 17 projects from the Investment and Construction Project Management Board of Region I to continue managing and implementing them.

By November 20, 2026, all 20 projects carried over from 2025 will have been completed and approved for final settlement, with 16 projects fully settled. Of the 22 new projects scheduled to start in 2026, 6 have been completed, and 16 are under construction according to schedule. Notably, in the last six months of 2026, Uong Bi ward will add 12 projects with a total investment of over 283 billion VND, focusing on upgrading transportation infrastructure, improving drainage systems, urban beautification, and public works.
For the 17 projects received from the Investment and Construction Project Management Board of Region I, the ward continues to focus on completing settlement and finalization procedures and accelerating the progress of the remaining projects. Among them, the Thanh Son 6 resettlement area project is under construction, with the embankment, land leveling, and electrical works completed 100%; sidewalks and drainage systems 95%; and roads 40%. The local authorities are coordinating to resolve on-site issues and facilitate the completion of the project.
Alongside accelerating construction progress, Uong Bi ward is focusing on the disbursement of public investment funds. By November 20, 2026, the total disbursed value reached over 202 billion VND. The locality strives to disburse 100% of the adjusted capital plan in 2026.
However, the implementation of these projects still faces some difficulties, especially in land clearance, persuading residents to donate land, and demolishing structures to facilitate construction. In addition, shortages and high prices of some materials are affecting the progress of the projects. The allocation of funds for undergrounding and relocating the power system has also caused the renovation projects on Nguyen Trai and Phan Dinh Phung streets to be temporarily suspended for adjustments to the scale and investment plan.
Comrade Hoang Huy Toan, Director of the Uong Bi Ward Service Supply Center, said: To accelerate the progress of construction projects, the Center continues to closely coordinate with specialized departments and residential areas to promote propaganda and mobilize people to agree to donate land, dismantle structures, and hand over the land for construction. At the same time, it regularly reviews the progress of each project, promptly resolves difficulties and obstacles; urges contractors to concentrate manpower, machinery, and equipment to accelerate construction progress and ensure the quality of the works. In particular, it proactively coordinates with the electricity sector to resolve obstacles in undergrounding and relocating the power system in urban beautification projects. The Center strives to complete construction and finalize accounts for 22 projects started at the beginning of the year and additional projects currently underway; and at the same time, accelerate investment preparation and contractor selection for the remaining projects, contributing to the completion of the public investment plan and capital disbursement in 2026.