The People's Committee of Lao Cai province has just issued Decision No. 4361/QD-UBND approving the project to renovate and repair the roadbed and surface of Van Chan - Tram Tau (DT.174), section from Km11+00 to Km31+400.
The project is being implemented in Cau Thia ward, Tram Tau commune and Hanh Phuc commune, with a total length of approximately 20.4 km.
This project belongs to group B, a level IV transportation project, and is designed according to the standards of a level V mountain road.

According to the approved plan, the road will essentially retain its existing alignment, utilizing the old roadbed and surface to minimize land acquisition and impact on structures along the road.
The road base is 6.5 m wide, and the road surface is 3.5 m wide; in some locations with favorable conditions, the road surface can be widened to 5.5 m.
The main items include roadbed improvement, asphalt concrete paving on a crushed stone base; repair and supplementation of drainage ditches and culverts; and reinforcement of landslide-prone and landslide-prone areas with gabion retaining walls.
The traffic signaling and safety systems have also been completed, and power lines have been moved outside the construction area.
The investment aims to address the deterioration of the road, improve its operational capacity, ensure safe and smooth traffic flow, and enhance connectivity with National Highway 32 and National Highway 37.
This will meet the needs for travel and transportation, contributing to the promotion of socio-economic development, tourism, and ensuring national defense and security in the locality.
The total investment for the project is 175 billion VND, sourced from the central government budget and the provincial budget.
The Project Management Board for Investment and Construction No. 1 of Lao Cai province is assigned as the investor, responsible for organizing the implementation, managing quality, quantity, progress, and costs according to regulations.
The People's Committee of Cau Thia ward and the People's Committees of Tram Tau and Hanh Phuc communes are responsible for coordinating the handover of land, land management, construction order, and creating conditions for the project to be implemented on schedule.