Member of the Central Committee of the Party, Deputy Secretary of the Provincial Party Committee, and Chairman of the Provincial People's Committee Ho Van Muoi chaired a meeting with investors and construction units regarding the progress of disbursing public investment funds.

On the afternoon of October 3rd, Mr. Ho Van Muoi, Member of the Central Committee of the Party, Deputy Secretary of the Provincial Party Committee, and Chairman of the Provincial People's Committee, chaired a conference on the disbursement of public investment capital for the first nine months of 2026 and the implementation of tasks for the last three months of the year.

Speaking at the conference, Chairman of the Provincial People's Committee Ho Van Muoi emphasized that the disbursement of public investment capital has seen a significant improvement recently.

The disbursement rate increased from 4% in the first quarter of 2026 to nearly 55% in the third quarter of 2026. In the third quarter alone, the entire province disbursed over 4,500 billion VND. This result is a testament to the decisive leadership of the provincial authorities and the involvement of various units and localities.

img_9577(1).jpg
Member of the Central Committee of the Party, Deputy Secretary of the Provincial Party Committee, and Chairman of the Provincial People's Committee, Ho Van Muoi, requested that in public investment, investors and construction units must clearly define their responsibilities, and from there, take action and achieve concrete results.

Chairman of the Provincial People's Committee Ho Van Muoi acknowledged that there is not much time left in 2026, while the workload remains very large. This includes the total capital that needs to be disbursed from the transitional funds carried over from 2025.

"

Lam Dong province has no room for delays in disbursing public investment funds. Investors and contractors are participating with determination and resolve, carrying out their tasks to the end. Each unit clearly defines its responsibilities, and from there, acts and produces tangible results. These results will serve as the basis for evaluating and holding accountable the individuals and groups involved.

Member of the Central Committee of the Party, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee Ho Van Muoi

Chairman of the Provincial People's Committee Ho Van Muoi requested that, specifically regarding land clearance, the entire political system must be determined to participate. By October 30, 2026 at the latest, all public investment projects must complete land clearance. This is a command from the heart, from a sense of responsibility. If it is not completed, the responsibility will primarily lie with the localities.

img_9580.jpg
Provincial leaders and representatives from various departments and agencies attended the conference on public investment.

As of the end of September 2026, the disbursement of public investment capital in Lam Dong reached over 10,792 billion VND, nearly 55% of the total plan. Of this, the disbursement rate for Project Management Boards reached 47.56%; for departments and agencies over 56.8%; and for communes, wards, and special zones nearly 64%.

According to assessments, the province's disbursement rate is showing positive progress, gradually increasing month by month. However, to complete the disbursement plan, Lam Dong still needs a very large amount of capital to be implemented in the fourth quarter of 2026, approximately over 10,493 billion VND.

Chief of the Provincial People's Committee Office, Do Tan Suong
Chief of the Provincial People's Committee Office, Do Tan Suong, reported on the results of public investment capital disbursement throughout the province up to the end of September 2026.

To date, the province still has 58 project owners who have not met their targets, mainly concentrated in the Project Management Board sector. Nine project owners have disbursed funds below their KPIs, affecting the overall progress of the province. However, the commune, ward, special zone, and Land Development Center sectors have exceeded their commitments.

At the conference, investors and construction units reported on the disbursement progress and the difficulties and obstacles encountered in projects that are still behind schedule. Many proposals related to coordination in land clearance for projects were also clearly stated by the units.

Regarding the slow disbursement progress, Nguyen Vinh Binh, Director of the Dak R'lap Area Investment and Construction Project Management Board, explained that in 2026, the unit was assigned 10 projects with a total capital of over 184 billion VND. To date, the Board has only disbursed over 18 billion VND, reaching 10.2%.

The Director of the Dak R'lấp Regional Investment and Construction Project Management Board explains the reasons for the delays in the projects.
Nguyen Vinh Binh, Director of the Dak R'lap Area Investment and Construction Project Management Board, explains the reasons for the delays in the projects.

"The unit takes responsibility for the delays in the projects. This is largely due to poor coordination between the investor and the contractor. Some construction units also lack capacity. The Board is focusing on overcoming these shortcomings and is committed to disbursing all the funds allocated by the province," Mr. Binh pledged.

According to Vu Dang Thuy, Director of the Da Huoai Area Investment and Construction Project Management Board, the unit is currently implementing 26 projects. Of these, 21 are ongoing projects and 5 are newly started projects. To date, the Board has disbursed nearly 121 billion VND, reaching almost 42%.

The Director of the Da Huoai Area Investment and Construction Project Management Board reported on projects that are behind schedule.
Vu Dang Thuy, Director of the Da Huoai Area Investment and Construction Project Management Board, reported on projects that are behind schedule.

"Basically, the projects are progressing smoothly without any obstacles. The delays are due to a lack of responsibility and competence on the part of the construction unit. The Board is proposing a solution to replace the contractor if this continues to happen," Mr. Thuy affirmed.

According to Hoang Van Dong, Director of the Phan Thiet Area Investment and Construction Project Management Board, the unit has been allocated over 738 billion VND in 2026. Currently, five projects under the Board's management are behind schedule, with a total capital of approximately 166 billion VND. Most of these delays are due to slow land compensation and clearance processes.

img_9611.jpg
Hoang Van Dong, Director of the Phan Thiet Area Investment and Construction Project Management Board, provided information on the progress of delayed projects.

Regarding the disbursement task, the Director of Investment and Construction Project Management Board No. 3, Ha Sy Son, said that compared to the commitment with the province, the unit's disbursement progress is currently about 18% behind schedule. The main reason is that most projects are facing difficulties with land clearance.

Director of Investment and Construction Project Management Board No. 3, Ha Sy Son, reported on the difficulties encountered during the implementation of the projects.
Director of Investment and Construction Project Management Board No. 3, Ha Sy Son, reported on the difficulties encountered during the implementation of the projects.

According to Mr. Son, the Dao Nghia - Quang Khe road project (phase 2) is an example. To date, the main route of the project is still facing obstacles from 31 households. The unit has compiled a list and is continuing to coordinate with local authorities to persuade them to provide the land for the construction unit.

During the meeting, the project's construction units presented the reasons for the delay and committed to mobilizing manpower and machinery to accelerate construction work towards the end of the year.

Representatives from Son Hai Group - the joint venture contractor for the Dao Nghia-Quang Khe road project (phase 2) - reported on difficulties and obstacles encountered at the meeting.
Representatives from Son Hai Group - the consortium of contractors for the Dao Nghia - Quang Khe road project (phase 2) - reported on difficulties and obstacles encountered at the meeting.

Some contractors have requested an extension of the project completion time. The units have committed to being determined, making every effort, working overtime and extra shifts, to meet the project schedule.

The contractor's representative reported on the difficulties and obstacles encountered at the meeting.
The contractor's representative reported on the difficulties and obstacles encountered at the meeting.

Through proposals and discussions, specialized departments and agencies have requested that investors and contractors who have committed to the schedule must develop a detailed Gantt chart. Each completion milestone must be detailed and clear. Based on this, the specialized unit will have a basis to synthesize and accurately evaluate the results and related responsibilities.

Acting Director of the Department of Construction Cao Son Dung reported on the coordination between the department and investors in disbursing public investment funds.
Acting Director of the Department of Construction Cao Son Dung reported on the coordination between the department and investors in disbursing public investment funds.

Many departments and agencies have proposed that communes urgently hand over land for the project. For cases where contractors have been given numerous opportunities but are still behind schedule, the investor will advise the Provincial People's Committee to take decisive action. Units and localities should coordinate closely in land clearance for the project.

img_9571.jpg
Member of the Central Committee of the Party, Deputy Secretary of the Provincial Party Committee, and Chairman of the Provincial People's Committee Ho Van Muoi requested that each unit and locality clarify responsibilities in the implementation process, absolutely avoiding shirking or evading responsibility.

Assigning responsibilities to units in the remaining months of the year, Chairman of the Provincial People's Committee Ho Van Muoi emphasized that the province's GRDP growth is accelerating very well. However, to achieve the growth target of 10% or more in 2026, the pressure in the fourth quarter of 2026 is immense. In particular, the disbursement of public investment capital plays a key role in boosting growth.

img_9593.jpg
Construction units involved in projects within the province attended the meeting.

Chairman of the Provincial People's Committee Ho Van Muoi directed that there is no turning back in disbursing public investment funds. The entire political system must participate with determination and decisiveness. Each unit and locality must fairly take responsibility in the implementation process, absolutely without shirking or avoiding responsibility.

"

The construction units must enhance their sense of responsibility and stand alongside Lam Dong province in this crucial final stage. More than ever, this is the time for all units to strive to overcome all difficulties, ensure progress, and fulfill all commitments to the province.

Member of the Central Committee of the Party, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee Ho Van Muoi

Director of Investment and Construction Project Management Board No. 1, Nguyen Quang Tu, reported on the disbursement progress of projects under the unit's management.
Director of Investment and Construction Project Management Board No. 1, Nguyen Quang Tu, reported on the disbursement progress of projects under the unit's management.

The head of the Lam Dong Provincial People's Committee requested that any difficulties or obstacles encountered during the implementation process be reported promptly so that solutions can be found.

Heads of agencies, units, and localities involved in land clearance work should uphold a high sense of responsibility, coordinate closely, and proactively handle tasks within their authority. They should avoid relying on superiors and delegating all responsibilities to subordinates.

img_9600(1).jpg
Member of the Central Committee of the Party, Deputy Secretary of the Provincial Party Committee, and Chairman of the Provincial People's Committee Ho Van Muoi affirmed that Lam Dong province will not allow issues under the responsibility of individual agencies and units to affect the overall disbursement progress.

In cases requiring coordination and support from relevant departments, agencies, and units, the investor and construction unit should proactively propose and report immediately to the leaders of the Provincial People's Committee for timely monitoring and direction. Lam Dong absolutely does not allow issues that fall under the responsibility of individual agencies or units to affect the progress of disbursing public investment capital throughout the province.