The Vietnam Airports Corporation (ACV) has just submitted to the State Inspection Council its plan for organizing the acceptance testing of completed works and items serving commercial operation under component 3 of the Long Thanh Airport project ( Dong Nai ).

Accordingly, many items will be prioritized for acceptance testing in November and December to facilitate commercial operation. The remaining items, to be completed after December, will have their acceptance testing extended until May 2027.

The East wing passenger terminal will be inspected and approved in March 2027.

For package 5.10 (passenger terminal), the entire construction and equipment system in the West wing and central area will be conditionally accepted in December. The remaining works and equipment systems in the East wing are expected to be fully accepted by March 2027.

Nhà ga hành khách sân bay Long Thành (Ảnh: Nam Anh).
Long Thanh Airport passenger terminal (Photo: Nam Anh).

In package 7.8 (cargo terminal), priority items for commercial operation in December, such as structure, roof, perimeter walls, electrical rooms, medium-voltage rooms, equipment, etc., were partially inspected between November 25th and 30th. The facade, interior, electromechanical systems, information technology, etc., will be completed after December and inspected from December 24th to May 1st, 2027.

For package 11.5 (parking garage), the P2 parking garage, pedestrian bridge, infrastructure, and electromechanical systems are prioritized for completion, with acceptance testing expected between December 15-18. The P1 parking garage and the central block will be accepted on April 20, 2027.

Package 4.8 (port transportation and technical infrastructure) is expected to be conditionally accepted on December 15th, including key works such as the main access road, the road in front of the terminal, the elevated bridge, the technical tunnel, and the energy building. The remaining items of this package, along with the remainder of packages 4.11 (wastewater treatment) and 5.11 (information technology system), are expected to be fully accepted by March 2027.

At the airfield, package 4.12 (second runway) will undergo conditional acceptance on November 15th, and package 4.6 (runway, taxiway, aircraft parking apron) on November 29th.

Previously, Deputy Prime Minister Pham Gia Tuc requested ACV to coordinate with the People's Committee of Dong Nai City and relevant units to study options to ensure absolute security and safety; and to take care of the living and working conditions for workers during the phase of both operation and construction of the project.

Four bidding packages are being monitored regarding their progress.

In the concluding remarks of Deputy Minister of Construction Pham Minh Ha at the meeting to resolve difficulties and review the progress of component project 3, the Ministry requested ACV to work with contractors to clearly define the completion milestones for construction, equipment installation, acceptance testing, and single and integrated trial runs, thereby determining the specific time for putting the project into operation.

According to the Ministry of Construction, despite ACV's strenuous efforts to direct contractors to accelerate progress, the remaining workload of many packages under component project 3 is still very large, making it difficult to complete these project items in 2026.

Đoàn công tác của Phó Thủ tướng Thường trực Phạm Gia Túc thị sát công trường sân bay Long Thành (Ảnh: Nam Anh).
The delegation led by Deputy Prime Minister Pham Gia Tuc inspects the Long Thanh airport construction site (Photo: Nam Anh).

In the event that the project is not completed in 2026, an extension may be required. The Ministry of Construction requests ACV to urgently report to the competent authorities to adjust the project in accordance with regulations.

Prior to this, the Department of Economic and Investment Management of Construction and the State Inspection Department for Construction Quality conducted on-site inspections from October 28-30.

According to data from the Ministry of Construction, package 4.8 has reached over 82% completion, and package 5.10 has reached over 87%. Some packages, such as package 7.8, have only reached over 50% completion, and package 11.5 has reached nearly 45%.

ACV's periodic reports show that the construction volume of the contract packages only increases by 1-5% each month. The Ministry of Construction paid particular attention to the construction items of package 7.8, package 11.5, and the equipment items of package 5.10.

Deputy Minister Pham Minh Ha requested ACV to objectively assess the feasibility of completing the components of project 3, especially packages 5.10, 4.8, 7.8, and 11.5, in order to bring the project into operation as directed by the Government . The investor also needs to clarify specific solutions and measures to ensure that contractors complete the items as committed.

Review meeting on preparations for mining operations in November.

Regarding preparations for operation, on November 8th, the Ministry of Construction requested ACV to coordinate with the Civil Aviation Authority of Vietnam to develop a plan and operational methods for Long Thanh Airport in phase 1.

Bên trong nhà ga hành khách sân bay Long Thành (Ảnh: Hoàng Bình).
Inside the passenger terminal at Long Thanh Airport (Photo: Hoang Binh).

The Civil Aviation Authority is responsible for reviewing the plan and submitting the results before November 18th so that the Ministry can hold a meeting to review the preparations for operation in November.

The Department of Economic and Investment Management of Construction and the Vietnam Road Administration are tasked with inspecting and supervising expressway, national highway, and provincial road projects connecting to the airport, ensuring smooth traffic flow and preventing congestion when the airport becomes operational.

Previously, Deputy Prime Minister Pham Gia Tuc also assigned the Ministry of Construction to take the lead in reviewing and evaluating the necessary options and conditions to put Long Thanh Airport into operation and exploitation before December 31st.

According to ACV's announcement, the airport is expected to begin commercial operations from 0:00 on December 24th.