Eight bridge projects across the Red River and Duong River are currently being implemented in Hanoi , gradually forming a new transportation network, expanding urban development space, and strengthening regional connectivity. Thousands of officials, engineers, and workers, along with machinery and equipment, are being mobilized on construction sites stretching from the north to the south of the city. While some projects have exceeded their construction schedules, bottlenecks in technical infrastructure, land clearance, and construction organization still need to be addressed to ensure the projects are completed on time.

In recent years, rapid urbanization, along with population growth and increased traffic, has placed growing pressure on Hanoi's infrastructure. The Red River and the Duong River, while crucial to the urban spatial structure, have also created gaps in connectivity between areas on both banks. Many existing bridges frequently handle heavy traffic, especially during peak hours.
In this context, investing in the construction of new bridges not only addresses immediate traffic problems but is also a crucial step in the capital's urban spatial development strategy. As these projects are completed, the northern, eastern, southern, and western areas of the city will have more direct connections, facilitating efficient land use, attracting investment, and forming new growth centers.

In the eastern area, the Tran Hung Dao Bridge is expected to create another direct connection between the central area of Hanoi and the area east of the Red River. The project, approximately 4.18 km long, will not only help alleviate traffic congestion on existing bridges but also facilitate travel and trade between the two banks of the river.
Furthermore, the Tu Lien Bridge is a project of significant importance in connecting the inner city area with the northern part of the Red River. Upon completion, the bridge will create an additional direct transportation axis from the city center to the northern areas, contributing to the exploitation of the urban and service development potential of this region.

In the South, the Ngoc Hoi Bridge, Hong Ha Bridge, and Me So Bridge play a crucial role in completing the Ring Road 4 - Capital Region. These are indispensable links in forming an inter-regional transportation network, strengthening connections between Hanoi and neighboring provinces, especially Hung Yen . When these projects are put into operation, the transportation of goods, trade, and travel between localities will have more convenient options.

Meanwhile, the Thuong Cat Bridge and Van Phuc Bridge contribute to expanding connectivity in the western and northwestern areas of the city. These projects are expected to create more favorable conditions for people and businesses in trade, while also opening up opportunities for the development of areas with potential for urbanization, industry, services, and logistics.
The Le Chi Bridge, part of the Gia Binh connecting route, is also among the projects that Hanoi is promoting, contributing to supplementing the transportation connection in the Southeast. The creation of additional river crossings will help the transportation network no longer rely too heavily on a few existing bridges, thereby increasing the ability to distribute traffic flow across the entire system.
The importance of these projects has been repeatedly emphasized by city leaders during inspections and progress directives. At the meeting of the Steering Committee for Key Projects on August 12, 2026, the Chairman of the Hanoi People's Committee, Vu Dai Thang, requested project management boards to review all projects for which land has been secured, ensuring immediate and rapid implementation, and preventing unjustified delays.
This directive reflects the city's requirement for key infrastructure projects: not only must investment procedures be completed, but resources must be quickly converted into actual construction volume. For large-scale projects with long construction periods, delays in one stage can affect the progress of the entire project and related connecting transportation routes.

It is clear that the value of these eight bridges lies not only in their length, structural scale, or total investment. More importantly, each project will contribute to changing the accessibility of urban spaces, facilitating easier travel for residents, reducing transportation costs for businesses, and strengthening development linkages among localities in the region.

On the ground, the outlines of many bridges are gradually becoming clear. Bridge piers rise high over the river, and the foundations, piers, and girders are being constructed, gradually shaping large-scale transportation projects.
According to Report No. 821/BC-SXD dated November 6, 2026, from the Hanoi Department of Construction, among the 7 projects of bridges crossing the Red River that were monitored, 3 projects achieved construction values higher than the adjusted plan, including Tran Hung Dao Bridge, Hong Ha Bridge, and Me So Bridge.
Leading in terms of completion rate is the Tran Hung Dao Bridge. The construction value of the project reached over 3,366 billion VND, equivalent to 54.2% of the contract value, 4.3 percentage points higher than the adjusted plan. By early November, all 128 bored piles and 7 main bridge piers had been completed; the 5 piers in the middle of the river were basically structurally completed. Contractors are maintaining approximately 28 construction teams to implement the next items. According to the schedule assigned by the city, the Tran Hung Dao Bridge must be completed before June 30, 2027.
The Hong Ha and Me So bridges, part of the Ring Road 4 - Capital Region, also recorded positive results. The Hong Ha bridge achieved a construction value of nearly 2.126 billion VND, equivalent to 53.4% of the contract value, exceeding the adjusted plan by 0.9 percentage points. The Me So bridge achieved over 1.618 billion VND, equivalent to 50.1%, higher than the adjusted plan by 1.6 percentage points.

At these construction sites, a large volume of work is being carried out, from bored piles, pier foundations, pier shafts to superstructure components. For the Hong Ha Bridge alone, the construction units maintain approximately 30 work teams with over 700 staff and workers along the entire route. By early November, the project had completed all 941 bored piles, 69 out of 70 pier foundations, and the construction of the pier shafts at 65 out of 70 piers.
However, not all projects enjoyed similar favorable conditions. According to the Department of Construction's report, the Tu Lien Bridge achieved 26.8% of its construction value; the Ngoc Hoi Bridge achieved 26%; the Thuong Cat Bridge achieved 20%; and the Van Phuc Bridge achieved 35.6%. These percentages are all lower than the adjusted plan.
The main difficulties relate to additional land clearance, relocation of technical infrastructure, and construction conditions at some locations. At Tu Lien Bridge, although the land has been largely handed over according to the plan, the project is still hampered by two households at alley 310 Nghi Tam and the 110kV power line that has not yet been relocated. These factors are affecting the implementation of some foundation, abutment, and pier components of the bridge.
For the Ngoc Hoi bridge project, there are still obstacles related to 0.53 hectares of land on the Hung Yen side, 17 graves, and some electrical and water supply facilities. The Van Phuc bridge project has also not completed the clearance of an additional 1.48 hectares of land, preventing construction from proceeding as planned in some areas.
At a project progress review meeting on October 29th, Vice Chairman of the Hanoi People's Committee Bui Duy Cuong emphasized the role of the eight bridges in developing the transportation system, strengthening connectivity between areas, and creating momentum for the socio -economic development of the capital city. The city requested relevant departments, localities, and investors to focus on resolving difficulties, accelerating construction progress, and striving to complete the projects according to schedule.
One of the issues of concern to city leaders is ensuring the synchronization between the bridge project and the access roads and connecting traffic routes. In reality, a bridge can only be fully effective when the roads at both ends, the intersections, and the supporting infrastructure are developed in a unified manner and are capable of handling the traffic volume.
The city also requested a review of the contractors' actual capabilities and increased application of modern machinery, equipment, and technology to shorten construction time. Projects with available land must commence construction immediately, avoiding situations where land is left vacant while projects are behind schedule.
At Van Phuc Bridge, river flow conditions and water levels directly affect construction work. Engineer Nguyen Van Den, Deputy Construction Commander of VNCN E&C Investment and Construction Joint Stock Company, said that the average river water level at the time of the survey was about 1.5m, creating favorable conditions for the implementation of items under the river, especially the construction of the foundation and pit.

The Van Phuc Bridge project has a total investment of over 3,400 billion VND. Photo: Quang Thai
From this reality, it can be seen that each bridge project has its own specific construction conditions, requiring the investor and contractor to proactively develop appropriate technical plans. For projects crossing rivers, construction organization also depends on water levels, currents, foundation geology, and weather conditions. Therefore, maintaining multiple construction fronts simultaneously, preparing sufficient equipment, and having contingency plans are crucial requirements to ensure progress.
Another bottleneck that the city needs to address is the arrangement of locations for receiving excavated soil, sludge, and construction waste. Without a suitable collection and transportation plan, construction activities could be disrupted, incurring additional costs and impacting the environment. Therefore, relevant departments and agencies need to coordinate with local authorities to review locations, guide land use procedures, and organize waste treatment in accordance with regulations.
From now until the completion milestones in 2027, the workload at bridge projects remains very large. Therefore, accelerating progress is not only a requirement for each contractor on the construction site but also a responsibility for coordination among departments, localities, and investors. When the land is handed over in a timely manner, technical infrastructure is relocated synchronously, and construction resources are fully mobilized, the new bridge spans will have the conditions to be completed early, maximizing investment efficiency.
These eight bridges are not simply structures crossing rivers. They are also crucial links in Hanoi's strategy to expand development space, complete the transportation network, and strengthen regional connectivity. Each completed project will contribute a new connection route, facilitating travel for residents and businesses, and opening up development opportunities for areas on both sides of the river.