Along with the mobilization of large amounts of capital, a series of bridge projects across the Red River and ring roads are gradually moving from planning to concrete construction volumes, creating a need to improve the efficiency of resource utilization.

From the bridge pillars in the middle of the river…

At the Hong Ha Bridge construction site, rows of concrete pillars have risen above the water, preparing to receive the girder spans connecting the two banks. According to information released on November 14th, contractors have completed 941/941 bored piles, 69/70 pier foundations, and are constructing the pier bodies at 66/70 locations; the casting of Super-T girders, cantilever casting, and girder launching are being carried out simultaneously.

Not far from there, also on the Ring Road 4 - Capital Region, the Me So Bridge has 116 bored piles for the main bridge and 374 piles for the approach bridges. At the overpass bridge on the Hung Yen side, the piles, pier bases, pier shafts, and pier caps have been completed. On the branches connecting to the Heritage Road, 141 out of 186 bored piles have been constructed.

Hong Ha and Me So bridges are two crucial links on the Ring Road 4. At a progress review meeting chaired by Vice Chairman of the Hanoi People's Committee Bui Duy Cuong on the afternoon of October 29th, the Hong Ha bridge was reported to have reached 53% completion, exceeding the plan. The Me So bridge is approximately 50% complete and is expected to open for technical traffic in July 2027. When put into operation in conjunction with the expressway and interchanges, the two bridges will create additional river crossings, increasing transportation capacity between Hanoi and other localities in the Capital Region.

Construction site of Hong Ha Bridge on the Ring Road 4 - Capital Region. Photo: Hoai Nam/Vietnam+

Construction site of Hong Ha Bridge on the Ring Road 4 - Capital Region. Photo: Hoai Nam/Vietnam+

Speaking with a reporter from the Industry and Trade Newspaper, Professor, Doctor, and Distinguished Educator Tu Sy Sua, a senior lecturer at the University of Transport, emphasized that Hanoi's synchronized implementation of ring roads, bridges over the Red River, and the urban railway network will first and foremost contribute to improving connectivity between the central area and other areas of the city, while also strengthening links between the capital and neighboring provinces and cities.

According to him, when the network ensures connectivity within each mode and between modes, efficiency will extend to the entire urban transportation system. “ Traffic congestion in Hanoi is due to many objective and subjective reasons, mainly the imbalance between traffic demand and the capacity of transportation infrastructure, as well as urban traffic management. Developing a synchronized transportation infrastructure network will contribute to reducing congestion and improving the efficiency of infrastructure utilization ,” he stated .

In the central area, the Tran Hung Dao bridge is under simultaneous construction of the main bridge, approach bridges, and interchange. All 128 bored piles and 7 main bridge pier foundations have been completed. On the afternoon of November 16th, the first steel arch sections, weighing 62 tons each, were lifted and installed at the construction site; simultaneously, the approach bridge on the Long Bien side, the Co Linh interchange, and the approach bridge on the Hoan Kiem side were also under construction.

Construction site of Tran Hung Dao Bridge, a project connecting the city center with the eastern part of Hanoi. Photo: Anh Duong/An Ninh Thu Do (Capital Security)

Construction site of Tran Hung Dao Bridge, a project connecting the city center with the eastern part of Hanoi. Photo: Anh Duong/An Ninh Thu Do (Capital Security)

The Tran Hung Dao Bridge project has a total length of approximately 4.18km, of which the main bridge section spanning the river is 870m long, connecting the city center with the eastern part of the city. The construction location makes the project particularly significant for organizing the transportation network across the Red River. The project aims for completion before June 2027, adding another connection route for areas with high demand for travel and trade.

Simultaneously, construction on the Tu Lien, Thuong Cat, and Van Phuc bridges accelerated. At the Tu Lien and Van Phuc bridges, all the bored piles for the main bridge sections have been completed. The Thuong Cat bridge has completed 118 piles. The Tu Lien bridge has completed two main tower foundations. These projects, varying in scale, structure, and location, are simultaneously opening up new connecting routes across the capital's largest river.

…to the construction site and the already opened sections of road.

On the Ring Road 4 - Capital Region, the parallel road section from the Red River embankment to Thang Long Boulevard was opened for technical traffic in October and temporary traffic was organized from October 10th according to the plan of the competent authority. The remaining sections and intersections continue to be constructed according to plan.

The Ring Road 4 project has significance that extends beyond urban transportation. The route aims to connect production centers, industrial zones, logistics hubs, and inter-regional expressways. For businesses, convenient access between production areas and consumer markets is a crucial factor in organizing transportation, warehousing, and distribution of goods.

Professor Tu Sy Sua believes that Hanoi holds a special position in the national, regional, and international transportation network. “ For the Capital Region, Ring Road 4 plays a very important role: strengthening inter-regional connectivity and enhancing Hanoi's leading role as a hub for freight and passenger transport with neighboring provinces and cities ,” he emphasized.

According to experts, transportation infrastructure is closely linked to population distribution and production, trade, and service activities. When developed synchronously, infrastructure will create momentum for socio -economic development and adjust the urban spatial structure towards a green and sustainable direction.

On Ring Road 1, the Hoang Cau - Voi Phuc section has been open for technical traffic and temporary traffic management has been in place since September 2nd, after the city and local authorities completed land clearance. Construction continues on the two overpasses at the Lang Ha - Giang Vo and Nguyen Chi Thanh intersections, with completion expected in 2026. The remaining items will be completed during the temporary traffic management period.

The Ring Road 1 project, specifically the Hoang Cau - Voi Phuc section, is approximately 2.27 km long, with a 50 m wide cross-section and a total investment of over 7,210 billion VND. The image shows the section passing through Hanoi Obstetrics and Gynecology Hospital and the National Children's Hospital, which was completed and opened to traffic in early September 2026. (Photo: Tin Tuc va Dan Toc Newspaper)

The Ring Road 1 project, specifically the Hoang Cau - Voi Phuc section, is approximately 2.27 km long, with a 50 m wide cross-section and a total investment of over 7,210 billion VND. The image shows the section passing through Hanoi Obstetrics and Gynecology Hospital and the National Children's Hospital, which was completed and opened to traffic in early September 2026. (Photo: Tin Tuc va Dan Toc Newspaper)

Transforming resources into infrastructure capacity

According to data reported by the Hanoi Department of Finance at the regular meeting of the Hanoi People's Committee on November 6th, as of October 31st, Hanoi had disbursed 125,444 billion VND in public investment capital. This result is equivalent to 104.5% of the plan assigned by the Prime Minister and 75.95% of the plan assigned by the city after excluding a 5% savings, representing a 159.1% increase compared to the same period in 2025.

Simultaneously with bridge and road projects, the city is implementing urban infrastructure, drainage, environmental treatment, and five urban railway lines (lines 1, 2, 8, 10, and 14). Vice Chairman of the City People's Committee, Do Anh Tuan, emphasized that the requirement is "no longer simply about 'fast disbursement,' but about disbursing funds correctly for the projects," ensuring timely completion and generating actual output.

Besides the requirement to improve the efficiency of budget disbursement, mobilizing social resources through public-private partnerships (PPP) also places demands on project preparation progress, completion of procedures, and contract implementation. According to a report from the Department of Finance at a meeting chaired by the Chairman of the Hanoi People's Committee, Vu Dai Thang, on November 12th, since the PPP Law of 2020 came into effect, the city has implemented 14 PPP projects, including 12 BT projects and 2 BOT projects, among which is Component 3 of the Ring Road 4 - Capital Region. Of these, 4 projects have signed contracts and are currently being implemented. The Chairman of the People's Committee requested that relevant units urgently complete the preparation, appraisal, and approval of feasibility studies and sign contracts immediately thereafter; the Department of Finance will continue to act as the focal point for monitoring and supervising PPP projects.

For PPP projects, the value of work completed under the contract is a separate metric to monitor, in addition to the amount of budget capital disbursed. According to Report No. 821/BC-SXD dated November 6th from the Hanoi Department of Construction, the construction value of the Tran Hung Dao Bridge, a BT contract project, reached 54.2% of the contract value, the highest among the 7 Red River bridge projects being monitored. This ratio reflects the value of completed construction compared to the contract value, and is an indicator that needs to be distinguished from the disbursement rate of public investment capital. By mid-November 2026, the bored piles, bridge piers rising over the Red River, and sections of the ring road that had undergone technical traffic testing demonstrated the current progress of key infrastructure projects in the capital city.

However, the scale of capital mobilized and the high disbursement rate are only the initial conditions. The ability to complete projects on schedule, put them into operation synchronously, and maximize connectivity is the true measure of the investment process. This is also a requirement for infrastructure projects to truly expand development space, enhance competitiveness, and create more growth potential for Hanoi and the entire Capital Region.