On November 23, the Gia Lai Provincial People's Committee announced that it had requested localities with projects and plans for relocating and stabilizing residents in disaster-stricken areas to urgently organize a "40-day and night" intensive campaign; mobilizing the entire political system and local forces to participate in its implementation.

According to the Gia Lai Provincial People's Committee, the progress of implementing 16 projects and plans for relocating and stabilizing people in disaster-stricken areas has improved, but many tasks are still behind schedule.

Specifically, only 895 out of 1,351 households in the 2026 plan have had their old residences approved, leaving 456 households yet to be approved; construction has begun on 676 out of 1,225 houses, leaving 549 houses yet to be started. Some localities are experiencing particularly slow progress, such as Uar, Cat Tien, Phu My Dong, An Hoa, and Phu My Bac.

tp-c_img-659.jpg
New houses have been built for people in disaster-stricken areas. Photo: Truong Dinh.

During the "40 Days and Nights" campaign from November 20th to December 29th, Gia Lai province aims to commence construction on all houses included in the 2026 plan before November 30th; and complete the relocation of households with suitable housing before December 25th, 2026. Priority will be given to households living in areas at high risk of natural disasters.

The leaders of the Gia Lai Provincial People's Committee have requested that the Secretaries and Chairmen of the People's Committees of communes and wards directly supervise and take responsibility for the progress and results of implementation in their localities.

Along with housing construction, provincial leaders requested a focus on completing the infrastructure of resettlement areas. Specifically for the My Thang resettlement area (Phu My Dong commune), the Agricultural and Rural Development Project Management Board is concentrating maximum resources and organizing continuous construction in "3 shifts, 4 teams," including holidays; striving to basically complete the project before November 30th, prioritizing transportation, electricity, and water supply. The remaining resettlement areas must complete their infrastructure before December 31st, 2026.

Investors and People's Committees of communes and wards should proactively coordinate to complete payment and disbursement documents as soon as conditions are met. In cases where it is not possible to disburse all allocated funds, a report must be promptly submitted to clarify the reasons and responsibilities.