The delegation included: Tran Dang Quynh, Alternate Member of the Central Committee of the Party, Standing Deputy Secretary of the Provincial Party Committee; Nguyen Thanh Binh, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee; Nguyen Cao Son, Provincial Party Committee Member, Vice Chairman of the Provincial People's Committee; leaders of departments and agencies; Standing Committee of the Party Committees of communes and wards through which the project passes; representatives of construction contractors, design consultants and supervision consultants.
The delegation inspected the project to build, upgrade and expand the DT.477 road (section from Km1+500 to the bypass of National Highway 12B in Dong Phong commune, former Nho Quan district); the construction of Hoang Long bridge and access roads on the DT.477C route; and the project to build a road connecting the southern Red River Delta with the Northwest mountainous region and the North Central coastal region (Phase I).
At the inspection points, representatives from the Provincial Investment and Construction Project Management Board No. 1 reported on the implementation status of each project, the results of land clearance, construction, capital disbursement, and future implementation plans.

According to the investor's report, the project to build, upgrade, and expand provincial road DT.477; construct Hoang Long bridge and access roads on provincial road DT.477C has a total investment of 6,975 billion VND, with implementation time from 2025 to 2029. The project will be implemented in the communes of Gia Van, Dai Hoang, Gia Vien, Gia Hung, Gia Tuong, Gia Lam, Phu Son, Nho Quan, and Gia Phong.
The investment scope includes the construction and upgrading of the main route, approximately 22.37 km long, starting at Km1+500 of the DT.477 road, near The Vissai Cement Factory, and ending at the connection with National Highway 12B; and the construction of the new Hoang Long Bridge and approach roads at both ends of the bridge on branch route 1, approximately 3 km long, connecting the right embankment of the Hoang Long River in Gia Phong commune with the DT.477 road at the Bai Dinh Ba Sao intersection in Gia Vien commune. The main route and branch route 1 are designed as a Class III road in flat terrain, with 4 lanes. Branch route 2, approximately 2.6 km long, connects National Highway 12B with Nho Quan Bus Station and will be upgraded and expanded to a Class III road in flat terrain, with 2 lanes.

The project commenced on September 16, 2026. To date, local authorities have handed over approximately 20 out of 27.9 km of land, reaching about 72%; in particular, land clearance has been completed in Gia Lam and Gia Hung communes. The contractor is currently operating 10 construction teams, including 8 on the main route and 2 at Hoang Long Bridge. The estimated construction volume is 102.5 billion VND, equivalent to 2.28% of the contract value. The capital plan allocated for 2026, including capital from 2025 with an extended disbursement period, is over 1,878.7 billion VND; over 650.1 billion VND has been disbursed, reaching 34.6%, for land clearance and some construction consulting costs.
Regarding future progress, localities are focusing on completing the remaining land clearance for agricultural land; relocating technical infrastructure; and clearing land for residential areas with resettlement plans and cemetery land. The project aims to complete construction in the third quarter of 2028.

Regarding the project to build an inter-regional connecting road between the southern Red River Delta and the Northwest mountainous region and the North Central coastal region (Phase I), the investor reported: The project has a total investment of VND 6,939 billion, including over VND 1,208 billion from the central budget and nearly VND 5,731 billion from the provincial budget; the implementation period is from 2025 to 2028.
The route is approximately 32.366 km long, passing through the communes of Binh Minh, Dinh Hoa, Lai Thanh, Yen Mac, Dong Thai and the wards of Trung Son and Tam Diep; it is a Class II road in a flat area, with 6-8 lanes, a design speed of 100 km/hour, and 60 km/hour in urban areas. In this phase, the project aims for an operating speed of 80 km/hour; simultaneously, it will construct bridges, traffic safety systems, drainage systems, lighting, and green spaces along the route.

The project commenced on June 18, 2026. To date, local authorities have handed over approximately 27.5 km of land, reaching 85%; the communes of Binh Minh and Dong Thai have completed land handover. The contractor is currently deploying 7 construction teams, including 6 teams for road construction and 1 team for bridge construction. The estimated volume of work completed is 500 billion VND, equivalent to 10.8% of the contract value.
The capital plan for 2026, including the 2025 capital with an extended disbursement period, is over VND 3,791.5 billion; over VND 3,205.6 billion has been disbursed, reaching 84.5%. The remaining land clearance volume mainly involves relocating and restoring technical infrastructure facilities and compensating for and supporting residential land with resettlement arrangements. According to the plan, localities strive to complete the relocation of technical infrastructure facilities before December 31, 2026, and complete land clearance for residential land before February 28, 2027. The investor aims to complete construction at least 3 months ahead of schedule.
At the inspection points, representatives of the contractors reported difficulties regarding the supply of construction materials and requested the province and relevant departments to address these issues to ensure the progress of the two projects.

After conducting on-site inspections and listening to reports, Provincial Party Secretary Tran Huy Tuan emphasized the importance of the two projects in completing the transportation infrastructure system, strengthening connectivity, and serving the socio-economic development of the province. He requested that all levels, sectors, and localities focus on leadership, direction, and coordination to resolve difficulties regarding land acquisition and material sources, creating conditions to accelerate construction progress.
Regarding land clearance, the comrade requested that priority be given to allocating funds for compensation, support, and resettlement. Party committees and authorities in the communes and wards where the project passes through should focus on resolving remaining issues according to each progress milestone; and urgently complete resettlement areas to provide housing for residents and hand over the land to the contractor. The construction of resettlement areas, relocation of technical infrastructure, and land clearance need to be coordinated to meet the requirements for implementing the project's components.
Regarding material sources, the Provincial Party Secretary requested the investor and the Project Management Board to coordinate with contractors to review and determine material needs according to the construction progress; register needs and research and propose mining exploitation plans under a special mechanism to serve the project. Relevant departments and agencies should proactively participate and coordinate in assessing the reserves, exploitation capacity, and supply of mines, especially sand mines in the province, as a basis for proactively securing supply. At the same time, they should review and utilize materials from licensed mines; research exploration options, assess reserves, and increase mining capacity to meet actual needs. Material supply plans must be linked to the construction plan of each project and promptly address difficulties for contractors.
The comrade requested the investor to continue to coordinate closely with departments, agencies, and localities during the implementation process, proactively resolving difficulties and obstacles in a timely manner; contractors should proactively implement construction solutions suitable to the site conditions and material sources, organize construction teams rationally, accelerate progress, and strive to shorten the completion time of the two projects.