According to the plan, the unit has a total of 666 meters that need to be processed, including 143 meters installed remotely (PA1), 122 meters installed via mobile modem (PA2), and 401 meters that need to be replaced directly on-site (PA3).

Recognizing the significant volume of meter replacements on-site, requiring considerable manpower and travel time, the Phu My Power Company's team proactively arranged their work, utilizing even their days off to expedite progress. Despite challenging weather conditions and terrain in coastal areas and aquaculture ponds, the work teams persevered, strictly adhering to technical procedures and safety regulations; and coordinating with customers to complete all necessary paperwork after meter replacement.

The working groups of Phu My Power Company are striving to speed up the installation and replacement of electricity meters according to the new electricity usage schedule.

In addition, the leaders of Phu My Power Company and the Trade Union Executive Committee regularly visit the work sites to encourage and support the workers, promptly identifying and resolving any arising difficulties, thereby motivating the work teams to complete their tasks.

As of November 24, 2026, Phu My Power Company had completed 485 out of 666 meters, achieving 72.82% of the plan. Specifically, the remote installation method was completed for 143 out of 143 meters (100%); the method via mobile modem was completed for 57 out of 122 meters (46.7%); and the direct replacement method was completed for 285 out of 401 meters (71.1%).

In the coming period, the unit will continue to maintain a deployment force throughout the weekend, focusing on handling the remaining 181 meters, including 116 meters replaced directly and 65 meters replaced via mobile modem; at the same time, coordinating with the Company's Business Department and the Gia Lai High-Voltage Grid Enterprise to resolve technical issues, determined to complete the entire volume before the deadline of December 13, 2026.

With a proactive, responsible, and highly determined spirit, Phu My Power Company is striving to ensure the progress of the transition to the new electricity usage time frame, contributing to the implementation of the electricity sector's policy and ensuring customer rights.