The Ministry of Industry and Trade has proposed early research into a 1,050km long ultra-high voltage ±800 kV direct current power transmission line connecting the South Central coastal region with the Red River Delta.

The project is expected to have a transmission capacity of 6,000-8,000 MW, with a preliminary total investment of nearly $3.5 billion.

This proposal is included in the revised Power Development Plan VIII, which is currently open for public comment. If implemented, this could be the first ultra-high voltage direct current transmission line in Vietnam, serving to transmit electricity from the central to the northern regions.

According to the proposed plan, the first substation, located in the South Central region, will receive electricity from the North Central and South Central coastal regions via the 500kV power grid. Here, the electricity will be converted from alternating current to direct current for transmission to the North.

Upon reaching the receiving station, the electricity is further converted back into alternating current to be integrated into the northern power grid system.

Currently, the North-South power transmission mainly relies on four 500kV alternating current transmission lines; of which, the first two lines were put into operation in 1994 and 2005 respectively; the third 500kV Quang Trach-Pho Noi line, consisting of two double circuits, was completed and put into operation in 2024.

According to estimates by the National Power Transmission Corporation (EVNNPT), during peak hot weather days, these four power lines can supply nearly 20% of the electricity output for the North.

Compared to the currently used AC transmission technology, high-voltage direct current (HVDC) transmission technology allows for the conversion of electricity from the 500 kV grid to direct current at the substation, transmission over long distances, and conversion back to alternating current at the receiving substation. This technology also allows for direct adjustment of transmission power along the line.

According to a preliminary comparison by the Institute of Energy, the ±800 kV DC transmission option has an investment cost of approximately US$3.47 billion, or about US$3.6 billion in current value. These two figures are the lowest among the options considered, which include a DC transmission option using a different technology and two AC transmission options at 765 kV and 1,000 kV.

Since the preparation and construction time for this project could take 7-10 years, the Institute of Energy recommends early research and investment preparation for this transmission line.

The demand for electricity transmission from Central to Northern Vietnam is projected to increase in the coming years, as the Red River Delta and the Southeast region continue to be the two largest electricity consumption centers in the country.

According to calculations by the Institute of Energy, the amount of electricity transmitted from Central to Northern Vietnam could increase from 32.8 billion kWh in 2027 to 47.4 billion kWh in 2030. During this period, the 500 kV grid will handle the entire increased transmission volume.

To meet the demand, the revised Power Development Plan VIII includes the addition of two 500kV transmission lines, namely the Vung Ang-Hoa Binh-West Hanoi line and the line connecting Quynh Luu, Quynh Lap, Nghi Son with Hung Yen.

After 2030, the demand for electricity transmission to the North is projected to continue increasing. By 2035, the amount of electricity supplied from the Central region to the Red River Delta could reach 90.5 billion kWh. Of this, the 500kV AC transmission line from the North Central region is expected to handle approximately 45.5 billion kWh, while the new ultra-high voltage DC transmission corridor will handle approximately 45 billion kWh.

(VNA/Vietnam+)