On November 23rd, Mr. Khong Minh Toan, the commander of the consortium of contractors for the project, stated that the contractors have essentially gathered all the necessary finishing materials such as paving stones, electrical and plumbing supplies, and lighting systems to begin implementing the project's components.
Currently, the units are focusing on construction, plastering, and tiling at the temple, memorial, gate, guardhouse, Management Board office, and auxiliary structures. Simultaneously, they are installing stone reliefs, water supply and drainage systems, lighting, and completing the courtyards, roads, and landscaping. Approximately 80-100 workers have been mobilized to work on the construction site to accelerate progress.

According to Mr. Toan, the biggest challenge currently is mobilizing highly skilled workers. Because the project has many unique architectural elements requiring high technical and aesthetic standards, finding and assigning personnel to meet the construction and completion requirements remains difficult. The contractor is continuing to recruit additional workers and arrange suitable construction plans to ensure the project stays on schedule.

The contractor, in coordination with relevant parties, seeks and supplements manpower; simultaneously, they request additional workers and organize appropriate overtime. The investor, contractor, and supervisory consultant maintain weekly inspections and monitoring to assess progress and promptly address any difficulties arising at the construction site.
By the end of Q3/2026, the project had disbursed over 94% of its planned capital for 2026. The contractor is striving to complete 100% payment of the allocated capital for the project by November, and is requesting the Project Management Board to balance and arrange additional funds to pay for the completed work.

The Hai Duong Martyrs' Memorial and Cultural Park Construction Project has a total investment of 200 billion VND and covers an area of approximately 2.5 hectares in Tan Hung ward. The project includes main components such as a martyrs' memorial, bell tower, drum tower, square, memorial monument, reliefs, along with a system of supporting structures and landscaping.

With the main design concept "Light of Thanh Dong," inspired by the light shining from the East Sea, the project aims to create a memorial space to honor heroes and martyrs, while also showcasing the historical and cultural identity of the Eastern region. Notably, the system of stone steles at the temple is expected to be inscribed with the names of 38,941 martyrs, expressing the gratitude of the Party Committee, government, and people to those who sacrificed for the independence and freedom of the Fatherland.
Upon completion, the project will become a cultural and spiritual center, contributing to the education of patriotic traditions and the principle of remembering one's roots for future generations, and creating a cultural highlight in the urban landscape of Hai Phong.