Expedite forest product exploitation and resolve land-related issues for the Vinh - Thanh Thuy expressway.

Regardless of holidays, and seizing every opportunity to stay close to the site, the Kim Bang commune authorities are focusing on directing and coordinating with relevant agencies and units to accelerate the progress of exploiting and utilizing forest products, while simultaneously resolving difficulties and obstacles in land clearance work.

Báo Pháp Luật Việt NamBáo Pháp Luật Việt Nam25/11/2026

The decisive involvement of the government, along with the sense of responsibility and consensus of the people, is helping to remove bottlenecks and create favorable conditions for the implementation of the Vinh - Thanh Thuy expressway project.

Intense action from the scene

Over the past few days, including Saturdays and Sundays, the People's Committee of Kim Bang commune ( Nghe An province), led by Mr. Le Quang Huy, Deputy Secretary of the Party Committee and Chairman of the People's Committee, has directly inspected the site and urged the progress of exploiting and utilizing forest products in the areas within the project's scope.

The delegation included representatives from the Department of Agriculture and Environment of Nghe An province, the Forestry and Forest Protection Sub-Department of Nghe An province, Thanh Chuong Forest Protection Unit, Thanh Thuy Forest Protection Station, Thanh Chuong Protective Forest Management Board, General Youth Volunteer Team 5, and other relevant agencies and units.

The amount of timber harvested from the project is enormous.
The amount of timber harvested from the project is enormous.

At the site, the delegation focused on inspecting the progress of forest product exploitation in areas where the auction had been completed; at the same time, they assessed the situation regarding the mobilization of manpower, machinery, and equipment, as well as the organization of exploitation, transportation, and cleanup of forest products by the winning bidders.

The inspection revealed that the units had proactively allocated personnel and formed numerous teams and groups to carry out the work at various locations.

However, the volume of timber requiring harvesting, transportation, and clearing remains large; progress in some areas has not met requirements, potentially affecting the handover schedule for the construction of packages XL03, XL04, and XL05.

In light of this situation, the Chairman of the People's Committee of Kim Bang commune requested the winning bidders to urgently increase manpower, supplement machinery and equipment, organize synchronized and scientific construction teams; accelerate the progress of logging, transportation and clearing of forest products, and avoid prolonged backlogs that could affect the overall progress of the project.

Along with the requirement for progress, the leaders of the commune's People's Committee emphasized that the units must strictly comply with the regulations of the law on forestry, focusing on ensuring labor safety, forest fire prevention and control, and environmental hygiene.

Accelerating exploitation must be linked to responsible implementation, ensuring safety and compliance with regulations.

Regardless of holidays, officials from Kim Bang commune directly inspect and supervise the work on-site.
Regardless of holidays, officials from Kim Bang commune directly inspect and supervise the work on-site.

In parallel with the above tasks, the People's Committee of Kim Bang commune continues to coordinate with the Land Registration Office of Nghe An province and the consortium of contractors for packages XL03, XL04, and XL05 to conduct on-site inspections and review the land clearance situation along the entire route, especially in the areas where waste disposal sites are located to serve the project's construction.

Following a review, the Nghe An Provincial Project Management Board has adjusted some of the land clearance boundary markers at the waste disposal sites to better suit the actual conditions.

Therefore, the inventory, compensation, and support work for some households is being continued, reviewed, and finalized by the relevant units in accordance with regulations.

Local leaders directly visiting the grassroots level to inspect and supervise at each location not only helps to promptly identify difficulties and shortcomings but also enhances the responsibility of units in the implementation process.

This demonstrates the proactive and decisive spirit of the local authorities in meeting the deadlines of key transportation projects.

Consensus creates momentum.

Besides the decisive involvement of the government and relevant agencies, the consensus and cooperation of the people are playing a crucial role in overcoming difficulties in land clearance work in Kim Bang commune.

Despite some remaining issues related to boundary adjustments, inventory, compensation, and support, many households have demonstrated a sense of responsibility, facilitating contractors' access to the site and construction, thus minimizing disruptions to the project's progress.

Recognizing that land clearance is not just an administrative task but also a process of mobilization and consensus building among the people, the Party Committee and government of Kim Bang commune always focus on staying close to the grassroots, understanding the thoughts and aspirations of the people; coordinating with specialized agencies, investors and construction units to promptly resolve arising issues.

Ensure that resource extraction is carried out in accordance with regulations and on schedule.
Ensure that resource extraction is carried out in accordance with regulations and on schedule.

The overarching requirement is to ensure project progress while fully implementing regulations on compensation, support, and protection of the legitimate rights and interests of affected people.

The exemplary conduct and responsibility of officials and Party members, along with the spirit of sharing and cooperation from households, have contributed to overcoming immediate difficulties and spreading a spirit of solidarity for the common good of the community.

The Vinh - Thanh Thuy expressway project is of significant importance in strengthening trade connections, improving transportation infrastructure, expanding development opportunities, and creating momentum to attract investment for Nghe An province.

Therefore, expediting land clearance, especially in areas for logging and waste disposal in Kim Bang district, is of practical significance for the project's implementation progress.

Contributing to bringing the project to completion on schedule.
Contributing to bringing the project to completion on schedule.

With the motto "Decisive government - People's consensus - Contractors' prompt action," Kim Bang commune continues to mobilize the synchronized participation of the entire political system, strengthen coordination with relevant agencies and units, focus on resolving each difficulty and obstacle, and create favorable conditions for contractors to carry out construction.

Every piece of land handed over, every obstacle resolved, every volume of timber harvested and cleared in a timely manner contributes to moving the project one step further.

This is not only the result of the efforts of the investor and contractor, but also a testament to the sense of responsibility and decisiveness of the local government and the unity of the people, working together for the development of their homeland, Nghe An.

RELATED ARTICLES

View all→
Apartment buildings are both prioritized for development in urban areas and protected in terms of ownership rights.
25/11/2026

Apartment buildings are both prioritized for development in urban areas and protected in terms of ownership rights.

Master plan for managing trade surplus and mitigating risks in international trade.
25/11/2026

Master plan for managing trade surplus and mitigating risks in international trade.

The Tax Department provides guidance to taxpayers on waiving business license fees and late payment penalties.
25/11/2026

The Tax Department provides guidance to taxpayers on waiving business license fees and late payment penalties.

Festival Logo
  • THE MINISTRY OF CULTURE, SPORTS AND TOURISM
  • Số 51 phố Ngô Quyền, phường Cửa Nam, thành phố Hà Nội.

Categories

  • HOME
  • NEWS
  • SCHEDULE

Connect with us

Powered by Techcity