Vice Chairman of the City People's Committee Tran Nam Hung has just signed a document directing the acceleration of disbursement of public investment capital and National Target Programs in the remaining months of 2026.

According to data from the State Treasury Region XIII as of November 9th, the disbursement rate of the 2026 capital plan for the 14 communes and wards under the responsibility of Vice Chairman of the City People's Committee Tran Nam Hung only reached 66.83%, 19.68 percentage points lower than the city-wide average and 5.20 percentage points lower than the average of the 93 communes and wards.

Notably, 6 out of 14 localities have not yet reached the target of disbursing 70% of funds by October 31, 2026, as stipulated in the Directive of the Da Nang City People's Committee. These localities include Tien Phuoc, Lanh Ngoc, An Thang, Dien Ban, Go Noi commune, and Dien Ban Dong ward.

Mr. Tran Nam Hung, Vice Chairman of the Da Nang City People's Committee, during an inspection of a project in the city.

Da Nang City has requested the six localities to seriously learn from their experiences, directly review each project, clearly identify the causes, responsibilities, and deadlines for resolution; and provide written commitments on progress, volume, and value of disbursement on a weekly basis.

If there continues to be no significant improvement, the Department of Finance will compile a report and submit it to the City People's Committee for consideration of the responsibility of the head of the department according to regulations; striving to achieve an average rate of 92.5% for the entire city by November 30, 2026.

Da Nang City continues to require localities to identify the disbursement of public investment capital as a key and urgent political task in the remaining months of 2026; focusing on decisive leadership and direction, clearly assigning responsibilities to specific individuals, tasks, and deadlines; and preventing delays in disbursement due to subjective reasons.

Furthermore, the goal is to achieve a disbursement rate of at least 90% of the planned capital for 2026 before November 30, 2026, a 100% disbursement rate for capital carried over from 2025 to 2026 before December 31, 2026, and a 100% disbursement rate for public investment capital in 2026 before January 31, 2027.

At the same time, direct project owners to urgently urge contractors to increase manpower, machinery, equipment, and materials, and accelerate construction progress. For projects that are unable to disburse the entire planned capital, promptly report to the Department of Finance for compilation and submission to the competent authority for consideration of adjusting the capital plan in accordance with regulations…