According to the plan agreed upon by local authorities and relevant agencies, traffic connecting to Long Thanh Airport will be divided into three main routes.

Specifically, vehicles from the center of Ho Chi Minh City and the Mekong Delta provinces can travel via three routes: the Ho Chi Minh City - Long Thanh - Dau Giay expressway through the Long Thanh interchange to component project 2 of the Bien Hoa - Vung Tau expressway; the Ben Luc - Long Thanh expressway through the Tan Hiep interchange to component project 2 of the Bien Hoa - Vung Tau expressway; or from the former Thu Duc City via Ring Road 3, Nhon Trach Bridge, DT.25C and T1 route.

For the route from the former Ba Ria - Vung Tau province, vehicles will follow component project 3 to component project 2 of the Bien Hoa - Vung Tau expressway to enter route T1, or follow National Highway 51 via DT.25C to reach the airport.

Vehicles from Dong Nai City and the northern provinces will connect via components 1 and 2 of the Bien Hoa - Vung Tau expressway, following National Highway 51 via Provincial Road 25C, or take the Ho Chi Minh City - Long Thanh - Dau Giay expressway (coming from Lam Dong) and turn onto component 2 to enter route T1.

Finalizing the plan for connecting transportation from Ho Chi Minh City and the Mekong Delta region to Long Thanh Airport - Photo 1.

In addition, local authorities will operate a public bus network that connects directly to the airport.

Regarding infrastructure progress, the Department's report states that all three component projects of the Bien Hoa - Vung Tau expressway now allow vehicles with fewer than 9 seats to circulate. Component project 1 is currently undergoing repairs on some sections and is scheduled for completion by December 31st, while component project 2 (maximum speed of 80 km/h) is expected to have its supplementary traffic management plan at the Tan Hiep interchange approved in early December to facilitate connection with the Ben Luc - Long Thanh expressway.

The two routes directly connecting to the airport, T1 and T2, have also been completed, are ready for operation, and are currently having toll booths installed. At the same time, the road surface repair project on National Highway 51 is expected to be completed by December 20th, and the packages for the Ho Chi Minh City Ring Road 3 will be completed in 2026.

To ensure seamless operation as soon as the airport becomes operational, the Vietnam Road Administration recommends that the Ministry of Construction urge Project Management Board 85, VEC, and ACV to expedite the completion of the remaining items. It also requests that these units agree on the maximum operating speed and include passenger and cargo vehicles serving airport operations in the overall traffic organization plan.