Member of the Standing Committee of the Provincial Party Committee and Vice Chairman of the People's Committee of An Giang province, Le Trung Ho, delivered a speech directing the working session.
At the meeting, Vice Chairman of the Provincial People's Committee Le Trung Ho acknowledged the efforts of all levels, sectors, the Phu Quoc Economic Zone Management Board, the investor, and strategic investors in implementing projects serving APEC 2027. He emphasized that the Provincial People's Committee and relevant departments will continue to listen, promptly consider and resolve difficulties and obstacles, and create favorable conditions to accelerate construction progress.
Regarding issues related to the power grid, water supply and drainage, and telecommunications infrastructure, the Vice Chairman of the Provincial People's Committee requested that the electricity and telecommunications units urgently relocate affected technical infrastructure; and specify the results and completion time.

Scenes from the working session.
Regarding mineral extraction, the Department of Agriculture and Environment continues to research, guide, and support units in implementing the project in accordance with legal regulations. For land clearance, the Phu Quoc Special Economic Zone People's Committee continues to review, identify, and mark specific boundaries, creating conditions for contractors to access the site and organize construction. For the remaining households, the Special Economic Zone People's Committee is studying appropriate solutions to ensure land clearance requirements and project progress as directed by the province.

Representatives from Phu Quoc Sun Company Limited (Sun Group) presented the perspective view of the Provincial Road 975 project.

Nguyen Thanh Tung, Head of the Phu Quoc Economic Zone Management Board, spoke at the working session.
According to a report from the An Giang Provincial Department of Construction, the Provincial Road 975 project (section from Provincial Road 973 - Phu Quoc Airport - Provincial Road 975 - Provincial Road 973) has a length of 19.2 km and a total adjusted investment of over 7,000 billion VND. The project commenced on September 22, 2025, and is expected to be completed on May 31, 2027. The contractor is a joint venture between OLYMPIA Co., Ltd. (OLP) and OLYMPIA Industrial Construction Co., Ltd. (OIC).
As of November 15th, the construction value reached 1,188,970/1,848,991 million VND, equivalent to 64.3% of the contract value. The construction site currently employs 539 workers and utilizes 290 pieces of machinery and equipment.
For the 10-lane section, the contractor has constructed 22.5/33km of utility trenches; 17/29.6km of longitudinal drainage culverts and 0.3/3.9km of reinforced concrete drainage ditches. The additional access road is currently being excavated and filled within the handed-over land area, with a length of approximately 11.35km.